Operator Conducts Commisioning Test and Operational Trial for a 5.15 Km Serpong-Balaraja Toll Road in Banten

- 07 July 2022 13:22 WIB
Police cars ready to escort a commissioning test and operational trial for a 5.15 kilometer-long Serpong-Balaraja toll road. (Photo courtesy of Sinar Mas Land)
Police cars ready to escort a commissioning test and operational trial for a 5.15 kilometer-long Serpong-Balaraja toll road. (Photo courtesy of Sinar Mas Land)

The toll road project is divided into three phases before a total 40 km-long toll roads are completed.

The first phase is section I for Serpong-Legok areas (±9,8 km), then it will be continued to section II for Legok-Pasir Barat areas (±11,5 km) before they start working on section III for Pasir Barat-Balaraja (±18,6 km).

All of those sections will connect to Jakarta-Serpong, Jakarta-Merak, and Jakarta Outer Ring Road toll road sections.